Homework 2 - Project Schedule Activities
Project
A project consists of the activities shown in the table below. Using this information
complete the following tasks:
A. Draw an activity on node network diagram.
B. Calculate the earliest start, earliest finish, latest start, latest finish, and slack
times for each activity.
C. Identify the critical path.